normal Progressive payment scheme (NPS)

Stage Name
Est Timeframe
Description
Payment
Stage 1
Est. 6 – 12 months
Completion of foundation work
10%
Stage 2
Est. 6 – 9 months
Completion of reinforced concrete framework of the unit
10%
Stage 3
Est. 3 – 6 months
Completion of brick walls of the unit
5%
Stage 4
Est. 3 – 6 months
Completion of roofing / ceilings of the unit
5%
Stage 5
Est. 3 – 6 months
Completion of electrical wiring, internal plastering, plumbing & installation of door & window frames of the unit
5%
Stage 6
Est. 3 – 6 months
Completion of carparks, roads, & drains serving the development
5%
Stage 7
Est. 3 – 6 months
Notice of vacant possession (Temporary Occupation of Permit - TOP)
25%
Stage 8
Est. 1 – 12 months
On certification of statutory completion (CSC)
15%